Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): UPIN 19102MF12T01
Vendor/Entity Legal Name (if applicable): Walter P. Moore and Associates, Inc.
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Request Summary (Agenda Caption):
title
Request for approval to execute an amendment to an agreement with Walter P. Moore and Associates, Inc. in the amount of $111,806.00, for Professional Engineering Services in connection with Creel Country Estates Subdivision Drainage Improvements - 2018 (Phase 2), UPIN 19102MF12T01, Precinct 2, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end
Background and Discussion:
Creel Country Estates is in the Spring Gully and Goose Creek watershed and in Precinct 2 in eastern Harris County. This project site is generally bounded by E Wallisville Road to the north, residential development to the west and east, and O207-01-00 to the south. Creel Country Estates is in unshaded Zone X. Portions of the existing water and wastewater systems on Lyndale Dr, Bonnieville Dr, and Cindyrella Dr need to be relocated due to utility conflicts. The scope of services includes the design of approximately 1,620 linear feet of wastewater and 1,000 linear feet of water lines. Additionally, the scope includes time spent reviewing utility conflicts and resolution options, preparing cost estimates, and meeting with the County and the Water Control & Improvement District to prepare this proposal.
Expected Impact:
This project seeks to strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Creel Country Subdivision. The additional scope in services allows the project design to progress forward and alleviate utility impacts in the proposed design.
Alternative Options:
The County could elect to fund the requested task or choose to reject it. However, if not approved, the project cannot be constructed.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
04/28/2020 |
1.g.5 |
Contract Amendment |
12/13/2022 |
59 |
Contract Amendment |
Location:
Address (if applicable): Creel Country Estates Subdivision
Precinct(s): Precinct 2
Fiscal and Personnel Summary |
Service Name |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
1070 - Mobility Fund |
$ |
$111,806.00 |
$111,806.00 |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Current Budget |
$ |
$111,806.00 |
$111,806.00 |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Request |
$ |
$111,806.00 |
$111,806.00 |
$ |
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: March 26, 2024
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., CFM, Director of Capital Project Infrastructure, Harris County Engineering Department
Attachments (if applicable): Agreement