Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No: 22/0143
Vendor/Entity Legal Name (if applicable): Yellowstone Landscape Central, Inc.
MWDBE Contracted Goal (if applicable): 32%
MWDBE Current Participation (if applicable): 33.80%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Yellowstone Landscape Central, Inc. in connection with final On-Call-Maintenance-Mowing in South & Northeast Areas - 2022, with a deduction in the amount of $12,917.70, Job No. 22/0143-1, UPIN 22101MF2JH01, Precinct 1, MWDBE Contracted Goal: 32%, MWDBE Current Participation: 33.80%.
end
Background and Discussion:
Project includes mowing service in South & Northeast Areas. The terms of services in connection with purchase order HCNTY-0000063795 is being closed at the request of the Precinct, and in accordance with the recommendation of Harris County Engineering Department.
Expected Impact:
The change allows the unused funds to be returned to the Precinct.
Alternative Options:
Continue with the project in accordance with the original scope.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
x Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
10/11/2022
260
Contract Award
Location:
Address (if applicable):
Precinct(s): Precinct 1
Fiscal and Personnel Summary
Service Name
Engineering
Current Fiscal Year Cost
Annual Fiscal Cost
Labor
Non-Labor
Total
Recurring Expenses
Funding Sources
Existing Budget
1070 - Mobility Fund
$
-$12,917.70
-$12,917.70
$
Choose an item.
$
$
$
$
Choose an item.
$
$
$
$
Total Current Budge...