Title: Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, adding 123 calendar days, with an addition in the amount of $323,326.00, Job No. 21/0309-8, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%.
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 20101MF1ET01
Vendor/Entity Legal Name (if applicable): Brookstone, LP.

MWDBE Contracted Goal (if applicable): 17%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, adding 123 calendar days, with an addition in the amount of $323,326.00, Job No. 21/0309-8, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%.
end

Background and Discussion:
Harris County Precinct One Administration Office and Service Center is a new two-story, approximately 37,000 sf building located at 2787 El Camino Street. The building will house the administrative leadership departments that serve the needs of the surrounding Harris County Precinct One community, and a well-equipped Multi-purpose Center that will accommodate the needs of the Precinct and its constituents.

This change in contract includes scope changes to steel work, skylight, roof design, topping slab, and general conditions with 123 additional calendar days.

Expected Impact:
Changes allow the completion of the project in accordance with the original intent of the project.

Alternative Options:
Should we not move forward with this change order we would not be able to include the added scope changes and general conditions with 123 additional calendar days.


Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
_ Flooding
_ Environment
X Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
11/9/2021
239