File #: 24-1593    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/14/2024 In control: Commissioners Court
On agenda: 3/26/2024 Final action: 3/26/2024
Title: Request for approval of a change in contract with Main Lane Industries, LTD in connection with final construction of Transportation Improvements near Texas Southern University - Cleburne St from Ennis St to Scott St - 2019, adding three calendar days, with a deduction in the amount of $133,225.47, Job No. 19/0265, UPIN 19101MF19801, Precinct 1, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): UPIN 19101MF19801; Job No: 19/0265

Vendor/Entity Legal Name (if applicable): Main Lane Industries, LTD

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Main Lane Industries, LTD in connection with final construction of Transportation Improvements near Texas Southern University - Cleburne St from Ennis St to Scott St - 2019, adding three calendar days, with a deduction in the amount of $133,225.47, Job No. 19/0265, UPIN 19101MF19801, Precinct 1, Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program.

end

 

Background and Discussion:

Project includes the reconstruction of Cleburne Street, from Ennis Street to Scott Street, including new traffic signals, lighting and pedestrian features.  The awarded contract amount was $10,378,513.90.  The construction was completed in 2022.

 

This change in contract includes:

                     Final item quantities adjustment to reduce the previous change in contract amount from $223,249.23 to $90,023.76.  The deduction amount is $133,225.47.  The final construction payment is $10,468,537.66.

 

Expected Impact:

Changes will cause adjustment to the original contract to reflect actual work performed due to actual field condition so that the project can be completed in accordance with the original intent.

 

Alternative Options:

Reduce the scope of work to avoid the areas where actual field conditions differ from the design drawings.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing                     

_ Public Health

x Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

09/24/2019

21.d.8.i

Contract Award

06/09/2020

1.k.1

Contract Amendment for additional funds and extension of project term

03/09/2021

30

Contract Amendment for additional funds and extension of project term

05/11/2021

27

Contract Amendment for additional funds and extension of project term

08/10/2021

59

Contract Amendment for additional funds and extension of project term

12/13/2022

53

Contract Amendment for additional funds and extension of project term

 

Location:

Address (if applicable):

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund ,Fund 3002

$

-$133,225.47

-$133,225.47

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

-$133,225.47

-$133,225.47

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

-$133,225.47

-$133,225.47

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: March 26, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Dr. Hatem Bastawisy, PE, (Interim) Senior Director of Project Delivery, Harris County Engineering Department

Attachments (if applicable): County Auditor’s Form 1258B