File #: 24-1550    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/14/2024 In control: Commissioners Court
On agenda: 3/26/2024 Final action: 3/26/2024
Title: Request for approval of a change in contract with SER Construction Partners, LLC, in connection with Holderrieth Road Drainage Improvements Project, with an addition in the amount of $48,124.84, Job No. 22/0369-11, UPIN 18104MF0R901, Precinct 3, MWDBE Contracted Goal: 27%, MWDBE Current Participation: 44.72%.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No: 22/0369

Vendor/Entity Legal Name (if applicable): SER Construction Partners, LLC

 

MWDBE Contracted Goal (if applicable): 27%

MWDBE Current Participation (if applicable): 44.72%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with SER Construction Partners, LLC, in connection with Holderrieth Road Drainage Improvements Project, with an addition in the amount of $48,124.84, Job No. 22/0369-11, UPIN 18104MF0R901, Precinct 3, MWDBE Contracted Goal: 27%, MWDBE Current Participation: 44.72%.

end

 

Background and Discussion:

This change in contract included adding additional cost due to unforeseen field conditions:

-                     Removing of 4-6-inches of concrete on the bottom of the manhole, to prevent the obstruction a proper seal at the end of the cure-in-place pipe.

-                     Plan drawings call to reconnect an existing 8" waterline service at station; however, no pay item exists for 8" water service connections.

-                     The plans specify the connection to existing manholes to accommodate the addition of new manholes, but no pay item was provided to compensate contractor for additional work.

-                     To facilitate Harris County standards for the driveway, two fence gate where impacted and relocation was needed to meet Harris County standards.

 

New Items added to the contract include:

                     Remove concrete at the bottom of sanitary manhole for the total amount of ($500.00)

                     8” Water Service Connection for the total amount of ($7008.09)

                     Core & boot for existing Sanitary Sewer manhole for the total amount of ($13,574.00)

                     Relocate fence gate for the total amount of ($27,042.75)

 

Expected Impact:

This change in contract allows the contractor to be appropriately compensated for the additional cost.

 

Alternative Options:

To provide Subsurface Utility Engineering (SUE) and identify and map underground utilities before construction project, but it would conflict with letting timeline.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing                     

_ Public Health

x Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

01/10/2023

326

Contract Award

06/27/2023

32

Contract Amendment for additional funds and extension of project term

08/29/2023

59

Contract Amendment for additional funds

08/08/2023

40

Contract Amendment for additional funds and extension of project term

08/08/2023

54

Contract Amendment for additional funds

08/08/2023

42

Contract Amendment for additional funds

08/29/2023

40

Contract Amendment for additional funds

08/29/2023

42

Contract Amendment for additional funds

10/10/2023

51

Contract Amendment for additional funds

12/05/2023

47

Contract Amendment for extension of project term

 

Location:

Address (if applicable): Holderrieth Road.

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other Funds 2601, 2699

$

$48,124.84

$48,124.84

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$48,124.84

$48,124.84

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$48,124.84

$48,124.84

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: March 26, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Dr. Hatem Bastawisy, PE, (Interim) Senior Director of Project Delivery, Harris County Engineering Department

Attachments (if applicable): County Auditor’s Form 1258B