Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Negotiation
Project ID (if applicable): 23101MF2W201
Vendor/Entity Legal Name (if applicable): Tolunay Engineering Group Inc.
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to negotiate with Tolunay Engineering Group Inc. for Professional Engineering Services in connection with construction materials testing and related services for The Hill at Sims/Scott Street Greenway Multi-Use Trail from Swingle Road to South Acres Drive, UPIN 23101MF2W201, Precinct 1.
end
Background and Discussion:
The project is to construct approximate 5,400 linear feet of 10-foot wide, 6-in thick concrete trail along west side of Scott Street from Swingle Road to South Acres Drive. The construction materials testing services are needed to support the project during construction.
Expected Impact:
This agreement will allow the firm to conduct field and laboratory testing on soil, concrete, and other various construction materials to ensure the material’s compliance with Harris County Engineering Department’s adopted standards and specifications as required by state law.
Alternative Options:
Construction materials testing is required by state law.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
09/29/20 |
3 |
Interlocal Agreement with Houston Parks Board for Hill at Sims Park Phase 1 |
03/08/22 |
22-1630 |
Interlocal Agreement with Houston Parks Board for Hill at Sims Park Phase 2 |
10/10/23 |
23-5956 |
Interlocal Agreement with Houston Parks Board |
Location: Scott Street from Swingle Road to South Acres Drive
Address (if applicable):
Precinct(s): Precinct 1
Fiscal and Personnel Summary |
Service Name |
Professional Services - CMT |
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Request |
$ |
$ |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date March 26, 2024
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., Senior Director of Capital Project Infrastructure, HCED
Attachments (if applicable): N/A