File #: 24-1066    Version: 1 Name:
Type: Negotiation Status: Passed
File created: 2/15/2024 In control: Commissioners Court
On agenda: 2/27/2024 Final action: 2/27/2024
Title: Request for approval to negotiate with MWA Architects for Professional Architectural/Engineering design services in connection with the Institute of Forensic Sciences Building Morgue Renovation/Expansion, located at 1861 Old Spanish Trail, UPIN 22270MF2H301, Precinct 1.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Negotiation

 

Project ID (if applicable): UPIN 22270MF2H301

Vendor/Entity Legal Name (if applicable): MWA Architects

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable):N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval to negotiate with MWA Architects for Professional Architectural/Engineering design services in connection with the Institute of Forensic Sciences Building Morgue Renovation/Expansion, located at 1861 Old Spanish Trail, UPIN 22270MF2H301, Precinct 1.

end

 

Background and Discussion:

On February 8, 2022, Commissioner’s court approved the Preliminary Investment Memo request of $1,500,000 to provide professional services for the detailed design of the forensic genetics lab relocation, the morgue expansion, the relocation of other HCIFS departments during renovation, and the design plan of floors currently occupied.  This is a request to use some of the previously approved funding for the professional design services for the morgue renovation/expansion.  This includes assessment and potential replacement of morgue and toxicology storage coolers.  All design work will be coordinated with the HVAC/MEP consultant.

 

Expected Impact:

The HCIFS morgue expansion is a necessity and must be accomplished as soon as possible.  The Medical Examiner Services have seen a dramatic increase in cases and decedents.  The morgue has outgrown its current cold storage space and must increase in capacity.  Also, in 2022, the morgue and toxicology freezers/coolers had to have emergency repair services.

 

The Institute of Forensic Sciences Building - Morgue Renovation project will include the renovation and technological updates of the Medical Examiner morgue area and autopsy suites, and the assessment and potential replacement of morgue and toxicology storage coolers.

 

 

 

Alternative Options:

Without the necessary increased morgue space, IFS will continue to have an overloaded decedent cooler storage with no room for overflow or growth.

 

Alignment with Goal(s):

   Justice and Safety

_ Economic Opportunity

_ Housing

x Public Health

_ Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/17/2019

4.i.7

Request for $1M in CP funding for the IFS long-term masterplan

12/17/2019

1.e.2

Authorization to negotiate with Page Southerland Page, Inc. for the Masterplan Study for the IFS Building.

5/19/2020

1.g.4

Approval of $86,000 for the Masterplan Study for IFS building.

12/15/2020

1.f.1

Approval of Amendment #1 for additional $31,400 for study efforts

12/14/2021

38.

Approval of Amendment #2 for additional $38,000 for morgue expansion study to complete study efforts.

 

Location: Institute of Forensic Sciences Building

Address (if applicable): 1861 Old Spanish Trail, Houston, TX  77021

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Department wide

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Commercial Paper

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: February 27, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Dr. Hatem Elbastawisy, P.E., (Interim) Senior Director of Project Delivery

Division, Harris County Engineering Department 

Attachments (if applicable): N/A