File #: 24-0919    Version: 1 Name:
Type: Utility Agreement Status: Passed
File created: 2/12/2024 In control: Commissioners Court
On agenda: 2/27/2024 Final action: 2/27/2024
Title: Request for approval to execute a Service Outlet Location Statement for installation of an electric meter with CenterPoint Energy, LLC and authorize the County Auditor to pay monthly bills for 21420 1/2 Aldine Westfield Rd, Humble, Texas 77338 (Treaschwig Rd A (Phase 1) - from 1,000' west of Aldine Westfield Rd to west of Cypress Creek - 2014) for electrical power serving a traffic signal, UPIN 14104MF08X01, Precinct 3.
Attachments: 1. 24-0919-Utility Agreement-UPIN_ 14104MF08X01- Treaschig at Aldine Westfield
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Utility Agreement

Project ID (if applicable): 14104MF08X01
Vendor/Entity Legal Name (if applicable): CenterPoint Energy, LLC

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval to execute a Service Outlet Location Statement for installation of an electric meter with CenterPoint Energy, LLC and authorize the County Auditor to pay monthly bills for 21420 1/2 Aldine Westfield Rd, Humble, Texas 77338 (Treaschwig Rd A (Phase 1) - from 1,000' west of Aldine Westfield Rd to west of Cypress Creek - 2014) for electrical power serving a traffic signal, UPIN 14104MF08X01, Precinct 3.
end

Background and Discussion:
Treaschwig Rd A (Phase 1) is a road project which includes installing a permanent signal to enhance traffic movement. The service outlet location statement is needed to establish electrical service from CenterPoint Energy to power the traffic signal.

Expected Impact:
Approval of the service outlet location statement will allow CenterPoint Energy to establish electrical service to the permanent traffic signal, which is needed to enhance the operation of the intersection Treaschwig Rd at Aldine Westfield Rd.

Alternative Options:
All traffic signals require a power source, which is typically obtained through CenterPoint Energy. Alternative options are to place a generator, which is not reliable, or not installed/remove the traffic from the intersection. Both options pose a public safety concern and will impact the operation and increase delay of the intersection.


Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ X Transportation
_ Flooding
_ Environment
_...