File #: 24-0865    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 2/12/2024 In control: Commissioners Court
On agenda: 2/27/2024 Final action: 2/27/2024
Title: Request for approval to execute an amendment with HR Green, Inc. in the amount of $48,907.00 for Professional Engineering Services in connection with Hufsmith-Kohrville Rd 3, UPIN 15104M23NP03, Precinct 3 (previously Precinct 4), Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): UPIN 15104M23NP03

Vendor/Entity Legal Name (if applicable): HR Green, Inc.

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval to execute an amendment with HR Green, Inc. in the amount of $48,907.00 for Professional Engineering Services in connection with Hufsmith-Kohrville Rd 3, UPIN 15104M23NP03, Precinct 3 (previously Precinct 4), Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County’s M/WBE Program.

end

 

Background and Discussion:

 

The County executed an agreement for Professional Engineering Services with HR Green, Inc. in 2015 and now seeks to amend the agreement for a seventh time.  This amendment will facilitate the re-design of a standard four (4) lane concrete boulevard in 100-foot ROW with a 32-foot raised median and underground storm sewer system for the updated limits from 700’ north of Ezekiel Road to approximately 400’ north of Boudreaux Road. 

 

Expected Impact:

 

This action will allow the firm to incorporate the necessary design changes for the update project limits. 

 

Alternative Options:

 

The alternative is to not revise the plans, and the plans will not be compatible with the needs of the updated project limits.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

3/10/15

1.a.2.b.6

Professional Engineering Services agreement approved on court agenda

9/27/16

1.a.2.c.4

First amendment to Professional Engineering Services agreement approved on court agenda

5/25/21

52

Second amendment to Professional Engineering Services agreement approved on court agenda

9/14/21

58

Third amendment to Professional Engineering Services agreement approved on court agenda

1/25/22

61

Fourth amendment to Professional Engineering Services agreement approved on court agenda

12/13/22

47

Fifth amendment to Professional Engineering Services agreement approved on court agenda

3/14/23

28

Sixth amendment to Professional Engineering Services agreement approved on court agenda

 

Location:

Address (if applicable):  Hufsmith-Kohrville Rd 3

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Professional Engineering Services

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$48,907.00

$48,907.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$48,907.00

$48,907.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$48,907.00

$48,907.00

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: February 27, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Dr. Hatem Bastawisy, PE - (Interim) Senior Director of Project Delivery - Harris County Engineering

 

Attachments (if applicable): Contract Documents