File #: 24-0989    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 2/14/2024 In control: Commissioners Court
On agenda: 2/27/2024 Final action: 2/27/2024
Title: Request for approval of change in contract No. 1 with Lecon, Inc, for the Lauder Stormwater Detention Basin - Phase 2, resulting in an addition of $1,732.24 to the contract amount. (Greens Bayou Watershed, Bond ID C-34, Project ID P500-06-00-E006, Job No. 22/0224, Precinct 2, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 48.75%).
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): P500-06-00-E006
Vendor/Entity Legal Name (if applicable): Lecon, Inc.

MWDBE Contracted Goal (if applicable): 17%
MWDBE Current Participation (if applicable): 48.75%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 1 with Lecon, Inc, for the Lauder Stormwater Detention Basin - Phase 2, resulting in an addition of $1,732.24 to the contract amount. (Greens Bayou Watershed, Bond ID C-34, Project ID P500-06-00-E006, Job No. 22/0224, Precinct 2, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 48.75%).
end

Background and Discussion:
The project consists of excavating the southern compartment of a stormwater detention basin within the former Castlewood subdivision to reduce flooding along the P138-00-00 channel that drains to Greens Bayou. Changes to the contract are required due to the following:
* Harris County Engineering Department's Permitting Review, which identified the need to change from two 18" Reinforced Concrete Pipes (RCP) to a single 24" RCP at the project driveway.
* The bid failed to establish a dedicated bid item for trench shoring for excavation.

Expected Impact:
This change in contract is needed in order to complete the construction contract for this project. The requested items will ensure the work is completed properly.

Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order for this $1,732.24 amount. The other option would be to cancel the contract and procure a new contractor. This is not recommended, as doing so would substantially delay the remaining work in the construction contract.

Alignment with Goal(s):