File #: 23-6822    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 11/6/2023 In control: Commissioners Court
On agenda: 11/14/2023 Final action: 11/14/2023
Title: Request for approval of a Professional Services agreement with Lockwood, Andrews and Newnam, Inc. for Construction Phase Services in the amount of $73,124.59 for the Recovery and Resiliency Division (RRD) Aldine Village East Subdivision Drainage Improvements - 2018, UPIN 24208MF33K01, Precinct 2, MWDBE Contracted Goal: 25%.
Sponsors: Mony Hossain
Attachments: 1. 23-6822-Consultant- Aldine Village CPS-Lockwood, Andrews and Newman (LAN), Inc.23GEN3143 Updated
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): UPIN 24208MF33K01 - Job No.: 23/0360
Vendor/Entity Legal Name (if applicable): Lockwood, Andrews and Newnam, Inc.

MWDBE Contracted Goal (if applicable): 25%
MWDBE Current Participation (if applicable):
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a Professional Services agreement with Lockwood, Andrews and Newnam, Inc. for Construction Phase Services in the amount of $73,124.59 for the Recovery and Resiliency Division (RRD) Aldine Village East Subdivision Drainage Improvements - 2018, UPIN 24208MF33K01, Precinct 2, MWDBE Contracted Goal: 25%.
end

Background and Discussion:
The Aldine Village Subdivision Drainage Improvements - 2018 (East Package) project consists of subdivision drainage improvements. Major work activities include replacing and upsizing storm sewer systems and reconstructing roadside ditches along Sellers Road between Ridgeland Court and Corvette Court, including culvert and driveway replacements, constructing a new storm sewer along Corvette Court, and constructing an extension of HCFCD channel Unit No. P118-25-01

The additional funds will cover the construction phase services agreement to allow for construction oversight of the project.

Expected Impact:
This project seeks to reduce flood risk and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. Engineering support during the construction of the improvements is a step in the process to reduce the financial, physical, and emotional burden flood damage places on homeowners and will reduce the financial impact of recovery costs to the Aldine Village Subdivision Project area, Harris County, and F...