File #: 23-6821    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/6/2023 In control: Commissioners Court
On agenda: 11/14/2023 Final action: 11/14/2023
Title: Request for approval of a change in contract with Allgood Construction Co., Inc. in connection with Tidwell Road from west of Greens Bayou to CE King Pkwy, adding 4 calendar days, with an addition in the amount of $16,490.40, Job No. 19/0305-3, Precinct 1, (project was awarded prior to launch of County's M/WBE Program).
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 19/0305
Vendor/Entity Legal Name (if applicable): Allgood Construction Co., Inc.


MWDBE Contracted Goal (if applicable): 0%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Allgood Construction Co., Inc. in connection with Tidwell Road from west of Greens Bayou to CE King Pkwy, adding 4 calendar days, with an addition in the amount of $16,490.40, Job No. 19/0305-3, Precinct 1, (project was awarded prior to launch of County's M/WBE Program).
end

Background and Discussion:

The project includes the construction of Tidwell Road 4-Lane Concrete Boulevard and Replace Greens Bayou Bridge. The Change Order includes additional time and cost for the Pedestrian Rail Turn Downs (4 days and $16,490.40) for the Tidwell Project.

The additional delays are due to a delay in obtaining the materials to install pedestrian railing turn-downs. This improvement was not part of the original contract documents.

Expected Impact:

The change allows the Contractor to incorporate a change in scope to the project without penalty associated with the delay.

Alternative Options:

Maintain the original scope of the project.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
10/29/2019
20.c.9.b
Contract Award
12/01/2020
1.k.2
Contract Amendment for additional funds and extension of project term
05/16/2023
50
Contract Amendment for additional funds and extension of project te...

Click here for full text