Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 20/0258; UPIN: 21208MF1WZ01
Vendor/Entity Legal Name (if applicable): Tree Guy LLC
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Tree Guy LLC in connection with Clearing of Right-of-Ways and Related Items for Harris County, adding 15 calendar days, with an addition in the amount of $6,534.00, Job No. 20/0258-1, UPIN 21208MF1WZ01, Precinct 3.
end
Background and Discussion:
The project is located in Crosby, TX, within Harris County. The section of Franta Addition Neighborhood that is within the scope of this project is bounded by Miller Wilson Road on the west, by Franta Road to the north, the existing shallow drainage swale on the east and the existing railroad embankment to the south. There are two segments of drainage channel proposed for improvement: a smaller swale draining due south from Franta Road to the railroad tracks, and a larger channel draining to the southwest toward Miller Wilson Road. The scope and proposed improvements include clearing and grubbing within and in the vicinity of these two channels as per the approved plans. Construction of these improvements to be performed by Tree Guy, LLC, ensures that the project is built in accordance with Harris County and Harris County Flood Control regulations.
The Change in contract request new items for the following:
* PCO-1: Hydro-mulching - Added New Item "Hydro-mulching" additional cost for the amount of $6,534.00 and added 15 days. Change in contract is due to the Hydro-mulching not being included in the initial contract with Tree Guy, LLC. Howeve...
Click here for full text