Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 21/0030
Vendor/Entity Legal Name (if applicable): Allgood Construction Co., Inc.
MWDBE Contracted Goal (if applicable): 0%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Allgood Construction Co., Inc. in connection with final construction of Gosling Road 3, adding 75 calendar days, with a deduction in the amount of $457,286.45, Job No. 21/0030-6, UPIN 15104MF0CC03, Precinct 3, (project was awarded prior to launch of County's M/WBE Program).
end
Background and Discussion:
The project includes reconstruction of the existing 2-lane asphalt roadway to a 4-lane concrete pavement section with appropriate drainage system within a 100-foot Right-of-Way.
This change in contract includes the following:
* Addition of 75 days to allow for the construction of a 3-foot-thick clay liner in the proposed detention basin in accordance with the requirements by the Harris County Flood Control District.
* The cost of installation of 2 - 4 section signal head on West Rayford Road and Gosling Road intersection (East Bound Lane). ($7,141.30 - Lump sum)
* The final adjustment which includes the (reconciliation of actual quantities used in construction against the bid quantities). Total = (-$464,427.75)
Expected Impact:
This action allows unused funds to be returned to Harris County and allows the Contractor to be compensated, and to complete the work.
Alternative Options:
No action can result in substandard construction.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flo...