Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Negotiation
Project ID (if applicable): UPIN - 19102MF12T01
Vendor/Entity Legal Name (if applicable): Tolunay-Wong Engineers, Inc.
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to negotiate with Tolunay-Wong Engineers, Inc. for Professional Engineering Services regarding Construction Materials Testing and related Services for Creel Country Estates Subdivision Drainage Improvements, UPIN 19102MF12T01, Precinct 2.
end
Background and Discussion:
This project includes 8421 linear feet of drainage improvements, infrastructure improvements and related within the Creel Country Estates Subdivision. Regrading the ditches and upsizing driveway culverts. Tolunay-Wong Engineer's, Inc. will provide construction materials testing services to support the project in construction.
Expected Impact:
This agreement will allow the firm to conduct field and laboratory testing on soil, concrete, asphalt and various other construction materials to ensure the material's compliance with Harris County Engineering Department's adopted standards and specifications as required by state law.
Alternative Options:
Construction materials testing is required by state law.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any): N/A
Date
Agenda Item #
Action Taken
Location:
Address (if applicable): Creel Country Estates.
Precinct(s): Precinct 2
Fiscal and Personnel Summary
Service Name
Professional Services - CMT
FY 24
FY 25
Next 3 FYs
Incremental Expenditures (do NOT write...
Click here for full text