File #: 23-6631    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 11/2/2023 In control: Commissioners Court
On agenda: 11/14/2023 Final action: 11/14/2023
Title: Request for approval of an agreement with Cobb, Fendley & Associates, Inc., in the amount of $908,092.74, to provide engineering, design, bidding and construction phase engineering services in support of major maintenance activities to restore channel conveyance capacity in Barker Reservoir watershed. (Barker Reservoir Watershed, Bond ID C-53, Project ID T100-00-00-X002, Agreement No. 2022-196, Precinct 4, MWDBE Contracted Goal: 20%).
Attachments: 1. 111423 AGMT COBB FENDLEY 2022-196 PCT 4 backup
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): T100-00-00-X002
Vendor/Entity Legal Name (if applicable): Cobb, Fendley & Associates, Inc.

MWDBE Contracted Goal (if applicable): 20%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of an agreement with Cobb, Fendley & Associates, Inc., in the amount of $908,092.74, to provide engineering, design, bidding and construction phase engineering services in support of major maintenance activities to restore channel conveyance capacity in Barker Reservoir watershed. (Barker Reservoir Watershed, Bond ID C-53, Project ID T100-00-00-X002, Agreement No. 2022-196, Precinct 4, MWDBE Contracted Goal: 20%).
end

Background and Discussion:
As a part of the Flood Control District's maintenance operations, the Flood Control District undertakes multiple projects to de-silt channels on a routine basis. The Flood Control District has a need for additional sediment removal projects and bank repairs within the Barker Reservoir to assure proper drainage into the reservoir. This project will improve storm water conveyance by restoring several channels within Barker Reservoir to the original capacity to hold and convey storm water. The project consists of the removal of sediment from various tributaries within Barker Reservoir and repairs along the banks where needed so that flows will not be interrupted. This project does not have a score using the 2022 Prioritization Framework because it is a channel maintenance project.

Expected Impact:
This item will authorize the prime consultant to begin engineering designs for removal of sediment in the channels and repair deficiencies noted within them. The Flood Control D...