Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD., P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Asset Management
Project ID (if applicable): 24101MF2ZN01
Vendor/Entity Legal Name (if applicable): North Harris County Regional Water Authority, a political subdivision of the State of Texas
MWDBE Contracted Goal (if applicable): Not applicable.
MWDBE Current Participation (if applicable): Not applicable
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval for a sale by Harris County of a 0.1338-acre Waterline Easement to North Harris County Regional Water Authority, from the Precinct 1 Non-Project Related ROW Sales & Abandonments project, tract NHCRWA 31B-27 Water Line Easement - Sale, for the appraised value of $4,196.00, and that the County Judge execute the Waterline Easement, UPIN 24101MF2ZN01, Precinct 1.
end
Background and Discussion:
The sale of this easement along Harris County property is to install, operate and maintain the North Harris County Regional Water Authority's water line in order to service this MUD District.
Expected Impact:
The proposed project will allow the North Harris County Regional Water Authority (NHCRWA) to supply wholesale drinking water to all the independent neighborhoods, municipal utility districts, small municipalities, and permitted well owners within its boundaries. NHCRWA's primary assignment is to develop and implement a strategy for complying with the Harris-Galveston Subsidence District's (HGSD) Regulatory Plan that requires a conversion from groundwater to alternate water via a 60% reduction of groundwater usage by 2025, and an 80% reduction of groundwater usage by 2035.
Alternative Options:
No Alternative Options.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
_ Flooding
_ Envir...