Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): 20104MF1BQ01
Vendor/Entity Legal Name (if applicable): Northpointe Water Control and Improvement District (WCID)
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of a Joint Participation Interlocal Agreement with Northpointe Water Control and Improvement District to construct drainage improvements from the Northpointe Blvd Segment 2 Project from Northpointe Ridge Lane to Northpointe Terrace Drive and all related appurtenances, Precincts 3 & 4.
end
Background and Discussion:
The Northpointe Blvd Segment 2 Capital Improvement Project (the Project) will widen the existing 2-lane concrete to 4-lane concrete boulevard of Northpointe Blvd, from Northpointe Ridge Lane to Northpointe Terrace Drive, with new drainage facilities.
The Project will result in drainage flowing to a detention pond owned and maintained by the Northpointe Water Control and Improvement District (the District), to ultimately outfall into the Faulkey Gully Cypress Creek (K142-00-00).
This agreement will allow Harris County runoff to convey through the District's facilities.
Expected Impact:
This project will improve mobility and safety for road users and flood resiliency for the adjacent properties.
Alternative Options:
Alternative options would be to divert the drainage runoff resulting in substantial increases in engineering design, property acquisition and construction costs.
Alignment with Goal(s):
X Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
X Environment
X Governance and Customer Service
Prior Court Action (if any): ...