File #: 23-2727    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/4/2023 In control: Commissioners Court
On agenda: 5/16/2023 Final action: 5/16/2023
Title: Request for approval of an amendment to an agreement with Sheldon Road Municipal Utility District to revise the budget for the Waterline Improvements Project, Project No. 2021-0031.
Attachments: 1. Sheldon Rd MUD Second Amendment_signed
Department: Community Services
Department Head/Elected Official: Thao Costis, Interim Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): C2021-0031
Vendor/Entity Legal Name (if applicable): Sheldon Road Municipal Utility District

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with Sheldon Road Municipal Utility District to revise the budget for the Waterline Improvements Project, Project No. 2021-0031.
end


Background and Discussion:
On February 9, 2022, Harris County Commissioners Court approved a CDBG-EN funded agreement in the amount of $438,224.00 in Program Year (PY) 2021 funds with Sheldon Road Municipal Utility District for the provision of the Waterline Improvements Project to provide services that meet the needs of low- and moderate-income individuals and families in Harris County.

On December 13, 2022, Harris County Commissioners Court approved a first amendment to the agreement with Sheldon Road Municipal Utility District revising the budget to increase the funding by $25,923.00 in PY2022 CDBG-EN funds. The project budget increased from $438,224.00 to $464,147.00 for the above referenced project.

The Community Services Department (CSD) is now requesting Commissioners Court approval of a second amendment to the agreement between Harris County and Sheldon Road Municipal Utility District to revise the budget to reallocate funding to cover costs for reimbursement of Davis Bacon and Related Acts (DBRA) and Section 3 compliance services completed by the Department of Economic Equity and Opportunity (DEEO).

Expected Impact:
The total project budget remains the same for a total of $464,147.00 in CDBG-EN funds.


Alternative Options:

No...