Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 23103MF2VZ01
Vendor/Entity Legal Name (if applicable): Quiddity Engineering, LLC.
MWDBE Contracted Goal (if applicable): 31.07%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Quiddity Engineering, LLC in the amount of $913,664.01 for Professional Engineering Services to provide improvements to Edgewater Park, UPIN 23103MF2VZ01, Precinct 3, MWDBE Contracted Goal 31.07%.
end
Background and Discussion:
Professional Services needed (design, engineering, and other pre-construction expenses) related to state/federal environmental and cultural/historical requirements needed to access the feasibility of constructing the Edgewater Park Boat Launch located at Hamblen Road near US 59, Harris County, Texas, Precinct 3.
Expected Impact:
The addition of this project will provide a safe and established boat launch location, an additional park for the growing community in the Kingwood region, and a further connection to the Spring Creek Greenway hike and bike trail will continue to offer public health benefits to the surrounding constituents.
Alternative Options:
If this request with Quiddity Engineering, LLC is not approved, this project will not be designed and lose grant funding provided by Texas Parks and Wildlife.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
X Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
8/2/2022 |
62 |
Authorization to Negotiate with Quiddity Engineering, LLC. |
8/2/2022 |
69 |
Request for approval to have project within Precinct 3 name changed. |
Location:
Address (if applicable): 202 Hamblen Road, Humble, TX 77339
Precinct(s): Precinct 3
Fiscal and Personnel Summary |
Service Name |
Professional Services |
|
FY 23 |
FY 24 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$913,664.01 |
$ |
$ |
Total Incremental Expenditures |
$913,664.01 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
1080 - Infrastructure Fund |
$913,664.01 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$913,644.01 |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$913,664.01 |
$ |
$ |
Total Funding Sources |
$913,664.01 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: May 16, 2023
Anticipated Implementation Date (if different from Court date): May 16, 2023
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Tristan Weinholzer, Project Manager, HCED
Attachments (if applicable): Agreement