Harris County Logo
File #: 23-2694    Version: 1 Name:
Type: Public Necessity Status: Passed
File created: 5/4/2023 In control: Commissioners Court
On agenda: 5/16/2023 Final action: 5/16/2023
Title: Request for approval to decree that the Harris County Flood Control District project serve a public purpose and public necessity requires that the Harris County Real Property Division be directed to acquire two fee simple tracts for the public project known as F212 Channel Conveyance Improvements, for the purpose of channel improvements. (Galveston Bay Watershed, Bond ID F-98, Project ID F212-00-00-C001, Precinct 2).
Attachments: 1. 051623 PN F212 CHANNEL CONVEYANCE IMP PCT 2 backup

Department: Flood Control District

Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Public Necessity

 

Project ID (if applicable): F212-00-00-C001

Vendor/Entity Legal Name (if applicable): N/A

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval to decree that the Harris County Flood Control District project serve a public purpose and public necessity requires that the Harris County Real Property Division be directed to acquire two fee simple tracts for the public project known as F212 Channel Conveyance Improvements, for the purpose of channel improvements. (Galveston Bay Watershed, Bond ID F-98, Project ID F212-00-00-C001, Precinct 2).

end

 

Background and Discussion:

This project was recommended and outlined in the Galveston Bay Watershed Planning study. The project consists of improvements to the existing F212 channel as well as the replacement of an existing reinforced concrete pipe storm sewer with a new box culvert. These improvements are needed to intercept uncontrolled sheet flows and provide capacity for 100-yr NOAA atlas 14 rainfall.

 

Expected Impact:

The recommended project will reduce damages for nearly all structures affected by the 100-year event.

 

Alternative Options:

The alternative to approving this item would be to deny this request which will delay progress on this project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

7/20/2021

145.

ATN

12/14/2021

117.

Award

 

Location: N/A

Address (if applicable):

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

N/A

 

FY 23

FY 24

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$

$

$

Total Incremental Expenditures

$

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: May 16, 2023

Anticipated Implementation Date (if different from Court date): Not applicable

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District

Attachments (if applicable): Findings and Declarations; Survey Description and Map