Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): NA
Vendor/Entity Legal Name (if applicable): E&C Engineers & Consultants Inc.
MWDBE Contracted Goal (if applicable): 100%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with E&C Engineers & Consultants Inc. in the amount of $197,140.00 for Professional Engineering Services to provide improvements to Annex 53 at 1001 Preston Ave., Houston, TX 77002, Precinct 1, MWDBE Contracted Goal 100%.
end
Background and Discussion:
The mechanical and lighting systems at Annex 53 are old and have reached their end of life. The consultant on this project will provide services consisting of architectural and MEP engineering design for the entire Annex 53 facility. This project is listed on the Capital Improvement Plan list for FY23.
Expected Impact:
Completion of this project will increase the reliability of the building’s critical infrastructure systems. This project will also prevent catastrophic MEP systems failure and disruption of service. This project will also upgrade the current lighting system to LED in support of the County’s Climate Action Plan.
Alternative Options:
The system is currently operating and could be maintained in that capacity; however, it is old and prone to breaking down. If the system breaks down, parts are no longer available for its repair due to the age of the equipment.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
_ Flooding
_ Environment
_x Governance and Customer Service
Prior Court Action (if any): NA
Date |
Agenda Item # |
Action Taken |
10/18/2022 |
120 |
Investment Memo |
10/18/2022 |
124 |
Investment Memo |
12/13/2022 |
105 |
Negotiation |
Location:
Address (if applicable): 1001 Preston Ave., Houston
Precinct(s): Precinct 1
Fiscal and Personnel Summary |
Service Name |
Professional Services |
|
FY 23 |
FY 24 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$197,140.00 |
$ |
$ |
Total Incremental Expenditures |
$197,140.00 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Commercial Paper |
$197,140.00 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$197,140.00 |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$197,140.00 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: May 16, 2023
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Jeff Parker, MEP Projects Manager, HCED - Technical Services
Attachments (if applicable): PSA with Engineers & Consultants Inc.