Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 23102MF2T601
Vendor/Entity Legal Name (if applicable): Concept Engineers, Inc.
MWDBE Contracted Goal (if applicable): 59.39%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Concept Engineers, Inc. in the amount of $326,956.81 for Professional Engineering Services to provide improvements to sidewalks along Woodforest Boulevard from the east bank of Greens Bayou to Freeport Street, UPIN 23102MF2T601, Precinct 2, MWDBE Contracted Goal 59.39%.
end
Background and Discussion:
Provide improvements to the pedestrian realm along Woodforest Boulevard from Freeport Street to Greens Bayou, including approximately 11,660 LF of 4' to 6’ wide sidewalks.
Expected Impact:
Shared use path, community connectivity
Alternative Options:
Provide other pedestrian route options that would require additional community engagement
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
9/13/2022 |
22-5478 |
Approval to negotiate with Concept Engineers, Inc. for Professional Engineering Services in connection with Sidewalks on Woodforest Boulevard from Freeport Street to Greens Bayou, UPIN 23102MF2T601, Precinct 2. |
Location: Woodforest Road
Address (if applicable): Woodforest Boulevard from Freeport Street to Greens Bayou
Precinct(s): Precinct 2
Fiscal and Personnel Summary |
Service Name |
Professional Services |
|
FY 23 |
FY 24 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$326,956.81 |
$ |
$ |
Total Incremental Expenditures |
$326,956.81 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Other |
$326,956.81 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$326,956.81 |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$326,956.81 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: May 16, 2023
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Luis Berrios, P.E., Senior Project Manager, HCED
Attachments (if applicable): Engineering Services Agreement.