Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 22/0344
Vendor/Entity Legal Name (if applicable): Sequeira Civil Construction, LLC
MWDBE Contracted Goal (if applicable): 100%
MWDBE Current Participation (if applicable): 100%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Sequeira Civil Construction, LLC, in connection with Schiel Road 1 - from East of SH-99 to West of Fairfield Place Drive, with an addition in the amount of $3,840.00, Job No. 22/0344-1, UPIN 18103N302202, Precinct 3, MWDBE Contracted Goal: 100%, MWDBE Current Participation: 100%.
end
Background and Discussion:
Project includes construction of a standard 4-lane concrete boulevard section on Schiel Road, from East of SH- 99 to West of Fairfield Place Drive.
Change includes installation of temporary 60-inch RCP under driveway:
• REIMBERSMENT OF COST FOR INSTALLATION OF 60 INCH RCP ($3,840.00), 0 days
Expected Impact:
Change allows the contractor to be compensated for temporary 60" RCP included in the scope of work and not accounted for in the unit bid items.
Alternative Options:
Reduce width of detour asphalt pavement and risk an unsafe driving condition.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
11/15/2022 |
240 |
Contract Award |
Location:
Address (if applicable): Schiel Road.
Precinct(s): Precinct 3
Fiscal and Personnel Summary |
Service Name |
|
|
FY 23 |
FY 24 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$3,840.00 |
$ |
$ |
Total Incremental Expenditures |
$3,840.00 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Other Fund 3109 |
$3,840.00 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$3,840.00 |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$3,840.00 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: May 16, 2023
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Julia Bond, P.E., Manager HCED-CPD
Attachments (if applicable): County Auditor’s Form 1258B