Harris County Logo
File #: 23-0657    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 1/23/2023 In control: Commissioners Court
On agenda: 1/31/2023 Final action: 1/31/2023
Title: Request for approval to execute an agreement with Geoscience Engineering & Testing Inc. in the amount of $68,884.00 for Professional Engineering Services for Construction Materials Testing and related Services for the reconstruction of Asphalt pavements in the Western Trails Subdivision, UPIN 23103MF2N501, Precinct 3 (Non-Divisible).
Attachments: 1. 23-0657 Consultant - 22-0325 Geoscience Western Trails Subdivision P3.pdf

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): 22/0325

Vendor/Entity Legal Name (if applicable): Geoscience Engineering & Testing Inc.

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  0% - Non-Divisible

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with Geoscience Engineering & Testing Inc. in the amount of $68,884.00 for Professional Engineering Services for Construction Materials Testing and related Services for the reconstruction of Asphalt pavements in the Western Trails Subdivision, UPIN 23103MF2N501, Precinct 3 (Non-Divisible).

end

 

Background and Discussion:

Reconstruction of asphaltic concrete pavement throughout the Western Trails Subdivision in Harris County Precinct 3.

 

Expected Impact:

Reconstructing these areas will improve pavement conditions thereby improving mobility and safety for all road users.  This purchase order will allow the firm to conduct field and laboratory testing on soil, concrete, asphalt, and various other construction materials.

 

Alternative Options:

Construction materials testing is required by state law. Thus, alternatives include executing an agreement for similar services to a different vendor or cancelling this construction project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/13/2022

106

Approved Authorization to Negotiate

 

Location:

Address (if applicable): Western Trails

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Professional Service - CMT

 

FY 23

FY 24

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$68,884.00

$

$

Total Incremental Expenditures

$68,884.00

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

1070 - Mobility Fund

$68,884.00

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$68,884.00

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$68,884.00

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: January 31, 2023

Anticipated Implementation Date (if different from Court date): N/A

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Corey D. Ritter, CMT Manager, CPD

Attachments (if applicable): Agreement