Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 20/0204
Vendor/Entity Legal Name (if applicable): Unitas Construction, Inc.
MWDBE Contracted Goal (if applicable): 0%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Unitas Construction, Inc. in connection with final construction of Peek Road from North of Grand Ventana Drive to North of Stockdick School Road, with an addition in the amount of $11,378.48, Job No. 20/0204-4, UPIN 17103N301003, Precinct 3, MWDBE Contracted Goal: 0% (project was awarded prior to launch of County’s M/WBE Program).
end
Background and Discussion:
Project includes construction of a 4-lane concrete boulevard with 32' median and underground storm sewer system along Peek Rd from North of Grand Ventana Drive to North of Stockdick School Road. Change includes reconciliation of actual items and quantities used in construction with the estimated quantities included for bidding purposes.
Expected Impact:
Change will allow contract payments to be reconciled with actual work performed on the project.
Alternative Options:
Perform the work in accordance with the estimated quantities rather than allowing adjustment to accommodate field conditions.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
09/15/2020 |
18.d.11.j |
Contract Award |
01/04/2022 |
39 |
Contract Amendment for additional funds and extension of project term |
07/19/2022 |
30 |
Contract Amendment for additional funds and extension of project term |
09/27/2022 |
72 |
Contract Amendment for extension of project term |
Location:
Address (if applicable): Peek Road.
Precinct(s): Precinct 3
Fiscal and Personnel Summary |
Service Name |
|
|
FY 23 |
FY 24 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$11,378.48 |
$ |
$ |
Total Incremental Expenditures |
$11,378.48 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
1070 - Mobility Fund |
$11,378.48 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$11,378.48 |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$11,378.48 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: January 31, 2023
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Julia Bond, P.E., Manager HCED-CPD
Attachments (if applicable): County Auditor’s Form 1258B