Title: Request for approval to negotiate with AECOM, Technical Services, Inc. for Professional Architecture and Engineering Services related to the planning and assessment of the infrastructure of Harris County detention facilities, Precinct 2.

Department: County Engineer

Department Head/Elected Official:  Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Negotiation

 

Project ID (if applicable):

Vendor/Entity Legal Name (if applicable):

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval to negotiate with AECOM, Technical Services, Inc. for Professional Architecture and Engineering Services related to the planning and assessment of the infrastructure of Harris County detention facilities, Precinct 2.

end

 

Background and Discussion:

The infrastructure systems in the various county detention facilities are experiencing escalating maintenance issues.  As 24/7 facilities, these systems need to operate reliably without jeopardizing operations and code compliance.  These systems include, but are not limited to fire/life safety infrastructure, domestic water systems, sanitary piping systems, lighting systems, security doors, and HVAC systems.

 

Expected Impact:

The project controls for the planning and assessment of the two main Harris County Detention facilities will determine the condition of the infrastructure systems and impact on operations.  The project recommendations will include the planning and assessment of current detention facilities such as improved medical facilities, prioritization of system rehabilitation or replacement, operational impacts, and life safety required updates.

 

Alternative Options:

Continue maintaining current facilities.

 

 

 

 

 

 

Alignment with Goal(s):

X Justice and Safety

_ Economic Opportunity

_ Housing

X Public Health

_ Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): 701 N. San Jacinto Street, 1301 Baker Street, and 1200 Baker Street, Houston, TX.  77002

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

 

 

FY 23

FY 24

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$

$

$

Total Incremental Expenditures

$

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date:  January 31, 2023

Anticipated Implementation Date (if different from Court date): N/A

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Susan Fraser, P.E., CFM, Assistant County Engineer, HCED

Attachments (if applicable): N/A