Harris County Logo
File #: 23-0680    Version: 1 Name:
Type: Report Status: Passed
File created: 1/23/2023 In control: Commissioners Court
On agenda: 1/31/2023 Final action: 1/31/2023
Title: Request for approval of a Study Report prepared by R. G. Miller Engineers for the Drainage Improvements to Timberlake Estates Subdivision - 2022, UPIN 19103MF17E01, Precinct 3 (project was awarded prior to launch of County's M/WBE Program).

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Report

 

Project ID (if applicable): UPIN 19103MF17E01

Vendor/Entity Legal Name (if applicable): R. G. Miller Engineers

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval of a Study Report prepared by R. G. Miller Engineers for the Drainage Improvements to Timberlake Estates Subdivision - 2022, UPIN 19103MF17E01, Precinct 3 (project was awarded prior to launch of County’s M/WBE Program).

end

 

Background and Discussion:

The project is located in northwest Harris County, primarily in the White Oak Bayou watershed and partially in the Cypress Creek watershed. It is north of Cypress North Houston Road, east of Huffmeister Road, and west of N. Eldridge Parkway. Timberlake Estates consists of roadside ditches that drain into HCFCD channel K163-00-00. The proposed improvements are to regrade the roadside ditches, install a storm sewer system beneath roadside ditches, convert an amenity pond into a detention pond and connect that to the drainage system for mitigation. This study report is an executive summary with supporting appendices of detail to describe the analysis and recommendations from the study phase to include surveying, geotechnical, environmental, and drainage recommendations to be utilized for the proposed design of the project.

 

Expected Impact:

This project seeks to reduce flood risk and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. This study report approval is a step in the process to reduce the financial, physical, and emotional burden flood damage places on homeowners and will reduce the financial impact of recovery costs to the Timberlake Estates subdivision homeowners, Harris County, and FEMA. The fiscal impact for this project will come from the 1080 Funding for the Recovery and Resiliency Division subdivision projects with the long-term goal of reducing drainage costs in the future. No impact to project schedule or staffing anticipated.

 

 

 

Alternative Options:

No alternative option for this project is possible other than performing no additional work. However, in this area, the subdivision will continue to be a risk of flooding and structural damage to homes in the community.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

x Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

12/17/2019

1.e.15

Authorization to Negotiate for Engineering Services

04/07/2020

1.g.7

Contract Award for Professional Engineering Services

 

Location:

Address (if applicable): Timberlake Estates Subdivision

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

 

 

FY 23

FY 24

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$

$

$

Total Incremental Expenditures

$

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$

$

$

Additional Budget Requested

1080 - Infrastructure Fund

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: January 31, 2023

Anticipated Implementation Date (if different from Court date): January 31, 2023

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Isabel Fung, Division Manager, Recovery and Resiliency Division, Harris County Engineering Department

Attachments (if applicable): Study Report