File #: 23-0191    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 12/28/2022 In control: Commissioners Court
On agenda: 1/31/2023 Final action: 1/31/2023
Title: Request for approval of an agreement with CivilTech Engineering, Inc., a Woolpert Company, in the amount of $996,244, to provide preliminary engineering services in support of improvements along Keegans Bayou, HCFCD Unit D118-02-00. (Brays Bayou Watershed, Bond ID F-07, Project ID D118-02-00-E001, Agreement No. 2022-164, Precincts 1 and 4, MWDBE Contracted Goal: 38.28%).
Attachments: 1. 01323 AGMT CIVILTECH 2022-164 PCT 1 AND 4 backup

Department: Flood Control District

Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): D118-02-00-E001

Vendor/Entity Legal Name (if applicable): CivilTech Engineering, Inc., a Woolpert Company

 

MWDBE Contracted Goal (if applicable): 38.28%

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of an agreement with CivilTech Engineering, Inc., a Woolpert Company, in the amount of $996,244, to provide preliminary engineering services in support of improvements along Keegans Bayou, HCFCD Unit D118-02-00. (Brays Bayou Watershed, Bond ID F-07, Project ID D118-02-00-E001, Agreement No. 2022-164, Precincts 1 and 4, MWDBE Contracted Goal: 38.28%).

end

 

Background and Discussion:

This project was recommended and outlined in the Keegans Bayou Watershed Planning Study. The project

consists of the construction of a series of detention basins along D118‐02‐00 and increasing the size of the

existing storm sewer line under Beltway 8 draining to D118‐02‐00. These improvements are estimated to

provide flood volume mitigation of 275 ac‐ft. This item is requested so that we may have the selected consultant begin the preliminary engineering and design of the improvements along D118‐02‐00-E001. This project scores in the 1st quartile under the 2022 Prioritization Framework approved by Commissioners Court.

 

Expected Impact:

The recommended project potentially provides up to 275‐ac‐ft of detention along D118‐02‐00 and benefits

residential areas along both sides of Beltway 8 north of West Airport Road. These improvements also reduce peak flows to Keegans Bayou from D118‐02‐00. The Flood Control District staff, including staff augmentation will manage an engineering consultant team to execute the preliminary engineering and design stages of this

project.

 

Alternative Options:

The alternative to approving this item would be to deny this request which will delay progress on this project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

05/10/2022

132.

ATN

 

Location: Series of stormwater detention basins along D118-02-00 within City of Houston.

Address (if applicable):

Precinct(s): Precincts 1 & 4

 

Fiscal and Personnel Summary

Service Name

 

 

FY 23

FY 24

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$900,000

$96,244

$

Total Incremental Expenditures

$900,000

$96,244

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Bonds

$900,000

$96,244

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$900,000

$96,244

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$900,000

$96,244

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: January 31, 2023

Anticipated Implementation Date (if different from Court date):

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District