Harris County Logo
File #: 23-0151    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 12/27/2022 In control: Commissioners Court
On agenda: 1/10/2023 Final action: 1/10/2023
Title: Request for approval of a change in contract with Conrad Construction Co., LTD in connection with Water Control Improvement District (WCID) 50 Drainage Improvement-2020, adding 49 calendar days, with an addition in the amount of $194,815.80, Job No. 21/0195-7, UPIN 21102MF1WF01, Precinct 2, MWDBE Contracted Goal 9%, MWDBE Current Participation 9%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD., P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 21102MF1WF01 - Job No. 21/0195
Vendor/Entity Legal Name (if applicable): Conrad Construction Co. LTD

MWDBE Contracted Goal (if applicable): 9%
MWDBE Current Participation (if applicable): 9%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Conrad Construction Co., LTD in connection with Water Control Improvement District (WCID) 50 Drainage Improvement-2020, adding 49 calendar days, with an addition in the amount of $194,815.80, Job No. 21/0195-7, UPIN 21102MF1WF01, Precinct 2, MWDBE Contracted Goal 9%, MWDBE Current Participation 9%.
end

Background and Discussion:
The Recovery and Resiliency Division subdivision drainage improvement project is located in Harris County Water Control and Improvement District 50 (WCID 50), El Lago, Texas. The project scope consists of the removal and disposal of existing storm sewer and installing storm sewer, waterline, pavement, bulkheads, sidewalks, pedestrian ramps and driveways. The existing asbestos-cement waterline cannot be supported in place while the proposed storm sewer is installed without significant breakage, water loss and repairs. The scope and proposed improvements include changes for:
* PCO 23 - New 8-inch Waterline, Crestwood St. WCID 50 requested that 2,030 linear feet of existing
asbestos-cement 8-inch waterline pipe along Crestwood St. be replaced with an approved polyvinyl chloride pipe to eliminate the conflict with the proposed storm sewer. Deletion of unused quantity of existing well- pointing bid item. Cost: $194,815.80. The change also includes 49 days: 5 days for utility conflict, 6 days for material delivery and 38 days for construction associa...

Click here for full text