Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E. PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): 19101MF13601
Vendor/Entity Legal Name (if applicable): CenterPoint Energy Houston Electric, LLC
MWDBE Contracted Goal (if applicable): NA
MWDBE Current Participation (if applicable): NA
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute a Facilities Extension Agreement with CenterPoint Energy Houston Electric, LLC and to authorize the County Auditor to approve a Purchase Order for $4,179.00 for the cost associated with the removal of inline poles in connection with Oak Glen Place Subdivision Drainage Improvements at 14026½ Sellers Road, Houston, TX 77060, UPIN 19101MF13601, Precinct 2.
end
Background and Discussion: CenterPoint requires signed Facilities Extension Agreement for easement request
for new service.
Expected Impact: CenterPoint requires signed Facilities Extension Agreement for a new service.
Alternative Options: There are no alternate options as CenterPoint is the one and only entity we can deal with in these matters.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
_ Flooding
_ Environment
X Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
9/13/22 |
#64 |
Facility Extension Agreement |
Location:
Address (if applicable): 14026 ½ Sellers Road Houston Tx 77060
Precinct(s): Precinct 2
Fiscal and Personnel Summary |
Service Name |
|
|
FY 23 |
FY 24 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$4,179.00 |
$ |
$ |
Total Incremental Expenditures |
$4,179.00 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
1080 - Infrastructure Fund |
$4,179.00 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$4,179.00 |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$4,179.00 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: January 10, 2023
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Isabel Fung, Program Management, Engineering
Attachments (if applicable): Facility Extension Agreement