Harris County Logo
File #: 23-0144    Version: 1 Name:
Type: Interlocal Agreement Status: Passed
File created: 12/27/2022 In control: Commissioners Court
On agenda: 1/10/2023 Final action: 1/10/2023
Title: Request for approval to execute a Joint Participation Interlocal Agreement with the City of Houston to share in the cost of an Engineering Design Concept Report for Aldine Westfield Road from Beltway 8 to Pine Tree Drive and all related appurtenances, UPIN 23102MF2NG01, Precinct 2.
Attachments: 1. 23-0144 Partnership - COH Aldine Westfield P2.pdf

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

 

Project ID (if applicable): UPIN 23102MF2NG01

Vendor/Entity Legal Name (if applicable): City of Houston

 

MWDBE Contracted Goal (if applicable):N/A

MWDBE Current Participation (if applicable):N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval to execute a Joint Participation Interlocal Agreement with the City of Houston to share in the cost of an Engineering Design Concept Report for Aldine Westfield Road from Beltway 8 to Pine Tree Drive and all related appurtenances, UPIN 23102MF2NG01, Precinct 2.

end

 

Background and Discussion:

An interlocal agreement was requested to assist in the preparation of an engineering Design Concept Report for the major transportation corridor to provide the necessary information in order to plan for further utilization of the roadway to facilitate current and future traffic and infrastructure.  The document is required by the City of Houston to provide for the Mobility and Planning Process.

 

Expected Impact:

This study will allow for the incorporation of current infrastructure design along with policies and programs that will provide for community input while meeting future transportation needs.

 

Alternative Options:

Postponing the study would lengthen the process to provide improvments along the corridor and stymie economic progress of the surrounding areas.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

X Flooding

_ Environment

X Governance and Customer Service

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): From Beltway 8 North to Pine Tree Drive

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

 

 

FY 23

FY 24

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$800,000

$

$

Total Incremental Expenditures

$800,000

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Other

$800,000

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$800,000

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$800,000

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: January 10, 2023

Anticipated Implementation Date (if different from Court date): N/A

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Peter Davies, Precinct 2 Coordinator, Harris County Engineering Department

Attachments (if applicable): Agreement, Exhibit A and B