Harris County Logo
File #: 23-0141    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 12/27/2022 In control: Commissioners Court
On agenda: 1/10/2023 Final action: 1/10/2023
Title: Request for approval to execute an amendment with KCI Technologies, Inc. in the amount of $50,256.00 for Professional Engineering Services to provide drainage improvements to Kolbe Road and Related Infrastructure, UPIN 19103MF16601, Precinct 3.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): UPIN 19103MF14801

Vendor/Entity Legal Name (if applicable): KCI Technologies, Inc. 

 

MWDBE Contracted Goal (if applicable): 0%

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval to execute an amendment with KCI Technologies, Inc. in the amount of $50,256.00 for Professional Engineering Services to provide drainage improvements to Kolbe Road and Related Infrastructure, UPIN 19103MF16601, Precinct 3.

end

 

Background and Discussion:

The project is in northwest Harris County, south of Cypress North Houston Road and east of Telge Road. It is located in the White Oak Bayou watershed. The existing drainage system consists of roadside ditches which outfall to the east of the Cypress Chase subdivision to HCFCD Channel E133-01-00. The scope and proposed improvements include bringing South Kolbe Circle, South Kolbe Drive, Village Circle, Scott Circle, and Laura Circle into compliance with Harris County Standards. Additionally, the proposed drainage design will consist of grate inlets located in the existing roadside ditches draining via circular pipes under a proposed swale. Additional design services are needed as part of this amendment to account for the changes in roadway configurations and project driveways.

 

Expected Impact:

This project seeks to reduce flood risk and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. This amendment is a step in the process to reduce the financial, physical, and emotional burden flood damage places on homeowners and will reduce the financial impact of recovery costs to the homeowners surrounding the Kolbe Road and Related Infrastructure improvements project, Harris County, and FEMA. The fiscal impact for this project will come from the 1080 Funding for the Recovery and Resiliency Division subdivision projects with the long-term goal of reducing drainage costs in the future. No impact to project schedule or staffing anticipated.

 

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it.  However, if not approved, the project area will continue to experience flood risk.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/17/2019

1.e.14

Authorization to Negotiate for Engineering Services

6/9/2020

1.f.13

Contract Award for Professional Engineering Services

10/26/2021

36

Amendment to Contract for Professional Engineering Services

5/10/2022

33

Amendment to Contract for Professional Engineering Services

 

Location:

Address (if applicable): Kolbe Road & Related Infrastructure Drainage Improvements

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Professional Services

 

FY 23

FY 24

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$50,256.00

$

$

Total Incremental Expenditures

$50,256.00

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

1080 - Infrastructure Fund

$50,256.00

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$50,256.00

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$50,256.00

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: January 10, 2023

Anticipated Implementation Date (if different from Court date): January 11, 2023                     

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Nate Wilson, Senior Team Lead Project Manager, Recovery and Resiliency Division, Harris County Engineering Department

Attachments (if applicable): Contract Amendment