Title: Request for approval of an agreement with Omega Engineers, Inc., in the amount of $830,825, for preliminary engineering and design services for HCFCD Unit Q100-00-00. (Cedar Bayou Watershed, Bond ID F-47, Project ID Q100-00-00-P004, Agreement No. 2022-93, Precinct 3, MWDBE Contracted Goal: 85%).
Attachments: 1. 011023 AGMT OMEGA 2022-93 PCT 3 backup
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): Q100-00-00-P004
Vendor/Entity Legal Name (if applicable): Omega Engineers, Inc.

MWDBE Contracted Goal (if applicable): 85%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of an agreement with Omega Engineers, Inc., in the amount of $830,825, for preliminary engineering and design services for HCFCD Unit Q100-00-00. (Cedar Bayou Watershed, Bond ID F-47, Project ID Q100-00-00-P004, Agreement No. 2022-93, Precinct 3, MWDBE Contracted Goal: 85%).
end

Background and Discussion:
Cedar Bayou (Q100-00-00) has a long history of flooding between IH-10 crossing and the Coastal Water Authority (CWA) canal. This project area was studied in the Cedar Bayou Flood Risk Reduction Study (FRRS) and part of the Cedar Bayou Watershed Bond Implementation Program. The preliminary engineering report (PER) is needed to determine the best use of flood mitigation along this channel between IH-10 and CWA canal, to identify the require ROW and support other large-scale flood reduction efforts in the Cedar Bayou Watershed along the IH-10 corridor. The preliminary engineering effort is complex and requires review of other past and ongoing efforts along Q100-00-00 and the surrounding area, detailed H&H modeling, right-of-way (ROW) identification and conceptual design. This court action is to request for approval to execute the agreement with Omega Engineers, Inc. for engineering services to provide a preliminary engineering study.

Expected Impact:
This project is part of the Cedar Bayou Bond Implementation Program that will reduce flood risks in the area. The outcome of the preliminary engineering report is to recomme...