File #: 23-0137    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 12/27/2022 In control: Commissioners Court
On agenda: 1/10/2023 Final action: 1/10/2023
Title: Request for approval to execute an amendment with Entech Civil Engineers, Inc. in the amount of $454,245.00, for Professional Engineering Services to provide improvements to North Eldridge Parkway from Spring Cypress Road to Gregson Road, UPIN 15104MF0D701, Precinct 3, MWDBE Contracted Goal 75%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 15104MF0D701
Vendor/Entity Legal Name (if applicable): Entech Civil Engineers, Inc.

MWDBE Contracted Goal (if applicable): 75%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval to execute an amendment with Entech Civil Engineers, Inc. in the amount of $454,245.00, for Professional Engineering Services to provide improvements to North Eldridge Parkway from Spring Cypress Road to Gregson Road, UPIN 15104MF0D701, Precinct 3, MWDBE Contracted Goal 75%.
end

Background and Discussion:
The County engaged Entech Civil Engineers, Inc., to amend their existing contract and Provide additional professional engineering services for the design and construction of a standard four (4) lane concrete boulevard segment of North Eldridge Parkway, from Spring Cypress Road to Gregson Road, from 2 lane asphalt to 4 lane concrete curb and gutter with 32' raised median. Entech Civil Engineers, Inc. is qualified to perform these professional services. The firm is registered with the Harris County Engineering Department Professional Services Registry.

Expected Impact: The project will address current and future traffic volumes, reduce delays, and provide safe mobility for residents, pedestrians and drivers.

Alternative Options: If no action is taken, the project will experience delays in improving mobility in the area.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
3/10/2015
1.a.2.b.5
Professional Services Agreement
5/9/2017
...

Click here for full text