Title: Request for approval to execute an agreement with IDCUS, Inc. in the amount of $389,621.11 for Professional Engineering and related services to provide improvements to sidewalks along Uvalde Road from Wallisville Road to Holly Park Drive, UPIN 23102MF2QS01, Precinct 2, MWDBE Contracted Goal 40%.
Attachments: 1. 23-0125 Consultant - IDCUS, Inc. Uvalde Rd P2.pdf
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 23102MF2QS01
Vendor/Entity Legal Name (if applicable): IDCUS, Inc.

MWDBE Contracted Goal (if applicable): 40%
MWDBE Current Participation (if applicable):0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with IDCUS, Inc. in the amount of $389,621.11 for Professional Engineering and related services to provide improvements to sidewalks along Uvalde Road from Wallisville Road to Holly Park Drive, UPIN 23102MF2QS01, Precinct 2, MWDBE Contracted Goal 40%.
end

Background and Discussion:
Provide improvements to the pedestrian realm along Uvalde Road from Wallisville Road to Holly Park Drive, including approximately 12,000 LF of 4' to 6' wide sidewalks.

Expected Impact:
Shared use path, community connectivity

Alternative Options:
Provide other pedestrian route options that would require additional community engagement

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
7/19/2022
22-4288
Approval to negotiate with IDCUS, INC for Professional Engineering Services in connection with Sidewalks on Uvalde Road from Wallisville Road to Holly Park Drive, UPIN 23102MF2QS01, Precinct 2.

Location: Uvalde Road
Address (if applicable): Uvalde Road from Wallisville Road to Holly Park Drive
Precinct(s): Precinct 2

Fiscal and Personnel Summary
Service Name
Professional Services

FY 23
FY 24
Next 3 FYs
Incremental Expenditures (do NOT write values in thousands or millions)
Labor Expenditures
$
$
$
Non-Labor Expenditures
$389,621.11
$
$