File #: 23-0092    Version: 1 Name:
Type: Negotiation Status: Passed
File created: 12/27/2022 In control: Commissioners Court
On agenda: 1/10/2023 Final action: 1/10/2023
Title: Request for approval to negotiate with Geotest Engineering, Inc. for Professional Engineering Services for Construction Materials Testing and related Services to construct Western Homes Addition Subdivision Drainage Improvements - 2018, UPIN 20102MF1E501, Precinct 2.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Negotiation

 

Project ID (if applicable): 22/0425

Vendor/Entity Legal Name (if applicable): Geotest Engineering, Inc.

 

MWDBE Contracted Goal (if applicable): N/A                     

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval to negotiate with Geotest Engineering, Inc. for Professional Engineering Services for Construction Materials Testing and related Services to construct Western Homes Addition Subdivision Drainage Improvements - 2018, UPIN 20102MF1E501, Precinct 2. 

end

 

Background and Discussion:

 

Construction of underground drainage utilities and reconstruction of driveways and roadway in the Western Homes Subdivision.

 

Expected Impact:

 

Constructing underground utilities and reconstructing the roadway will improve drainage and paving conditions, thereby improving mobility and safety for all road users and flood resiliency for all adjacent properties. This agreement will allow the firm to conduct field and laboratory testing on soil, concrete, asphalt and various other construction materials. This testing will ensure the material’s compliance with Harris County Engineering and other governing bodies specifications as required by state law.

 

Alternative Options:

 

Construction materials testing is required by state law. Thus, alternatives include executing an agreement for similar services to a different vendor or cancelling this construction project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): Western Homes Addition Subdivision.

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Professional Services - CMT

 

FY 23

FY 24

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$

$

$

Total Incremental Expenditures

$

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: January 10, 2023

Anticipated Implementation Date (if different from Court date): N/A

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Corey D. Ritter, CMT Manager, CPD