Department: Toll Road Authority
Department Head/Elected Official: Roberto Trevi?o, P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Proposals/Bids
Project ID (if applicable): N/A
Vendor/Entity Legal Name (if applicable): N/A
MWDBE Contracted Goal (if applicable): 18%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a project scheduled for advertisement for construction engineering and inspection services for projects related to the Barrier-Free Program (Countywide). MWDBE Contracted Goal: 18%.
end
Background and Discussion:
As part of the implementation of the Barrier-Free Program, construction engineering and inspection (CEI) services are needed to support projects related to the conversion to an all-electronic roadway environment. With Commissioners Court approval, the solicitation will be advertised for three weeks.
Expected Impact:
Identify qualified firms for the Project.
Alternative Options:
No other recommended solution for this identified need.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
Location:
Address (if applicable): N/A
Precinct(s): Countywide
Fiscal and Personnel Summary
Service Name
Tolling Operations
FY 23
FY 24
Next 3 FYs
Incremental Expenditures (do NOT write values in thousands or millions)
Labor Expenditures
$
$
$
Non-Labor Expenditures
$
$
$
Total Incremental Expenditures
$
$
$
Funding Sources (do NOT write values in thousands or millions)
Existing Budget
Choose an item.
$
$
$
Choose an item.
$
$
$
Choose an item.
$
$
$
Total Current Budget
$
$
$
Additional Budget Requested
Choose an item.
$
$
$