Title: Request for approval to initiate and proceed with a new bond project for Inverness Forest Levee Modifications. (Cypress Creek Watershed, Bond ID Z-04, Project ID K600-01-00-X016, Precinct 1).
Attachments: 1. 092722 NEW BOND PROJ AUTH K600-01-00-X016 PCT 1 backup

Department: Flood Control District

Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Report

 

Project ID (if applicable): K600-01-00-X016                                          

Vendor/Entity Legal Name (if applicable): N/A

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval to initiate and proceed with a new bond project for Inverness Forest Levee Modifications. (Cypress Creek Watershed, Bond ID Z-04, Project ID K600-01-00-X016, Precinct 1).

end

 

Background and Discussion:

Modifications and repair to the Inverness Forest levee will be required to assure that all standards are met under Atlas 14 and MAAPnext requirements, thereby allowing for recertification and acceptance by FEMA.

 

Expected Impact:

This project will allow for continued classification as a FEMA Zone X for the area behind the levee rather than being reclassified as a Zone AE for the residents of Inverness Forest subdivision.

 

Alternative Options:

Taking no action will result in decertification of the levee and leaves the residents who live behind the levee subject to potentially being mapped into the AE Zone which will result in significantly higher flood insurance costs.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

 

 

 

 

Location: N/A

Address (if applicable):

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

N/A

 

SFY 22

FY 23

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$

$

$

Total Incremental Expenditures

$

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Bonds

$

$

$

Other

$

$

$

Choose an item.

$

$

$

Total Current Budget

$

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: September 27, 2022

Anticipated Implementation Date (if different from Court date):

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Tina Petersen, Ph.D., P.E., Executive Director, Flood Control District

Attachments (if applicable): Map