Harris County Logo
File #: 22-5734    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/15/2022 In control: Commissioners Court
On agenda: 9/27/2022 Final action: 9/27/2022
Title: Request for approval of change in contract No. 2 with Lecon, Inc. for Major Maintenance of Cypress Creek and Tributaries Batch 1, with no change to the contract amount. (Cypress Creek Watershed, Bond ID CI-012, Project ID K100-00-00-X084, Job No. 21/0037, Precinct 3, MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program).
Attachments: 1. 092722 CIC NO. 2 LECON PCT 3 backup

Department: Flood Control District

Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): K100-00-00-X084                                          

Vendor/Entity Legal Name (if applicable): Lecon, Inc.

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval of change in contract No. 2 with Lecon, Inc. for Major Maintenance of Cypress Creek and Tributaries Batch 1, with no change to the contract amount. (Cypress Creek Watershed, Bond ID CI-012, Project ID K100-00-00-X084, Job No. 21/0037, Precinct 3, MWDBE Participation Goal: N/A - project was awarded prior to launch of County’s M/WBE Program).

end

 

Background and Discussion:

Unforeseen site conditions due to the additional erosion requiring additional rock and additional pipe and headwall/wingwalls has resulted in plan changes. Modifications to the design details to provide inlets with grating covers and extended channel lining has also resulted in plan changes. This requires an adjustment to plan quantities and addition of a new pay item. There is no net increase in the cost to the overall contract. No time extension is being requested.

 

Expected Impact:

This RCA is required to complete the District construction contract under original or needed revised scope.

 

Alternative Options:

This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

04/27/2021

233.

Award

05/24/2022

116.

Change in Contract No. 1

 

Location: Various Channels in the Cypress Creek Watershed, North and South of Spring Cypress Road between SH 249 and Kuykendahl Road.

Address (if applicable):

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

N/A

 

SFY 22

FY 23

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$

$

$

Total Incremental Expenditures

$

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: September 27, 2022

Anticipated Implementation Date (if different from Court date):

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Tina Petersen, Ph.D., P.E., Executive Director, Flood Control District

Attachments (if applicable): Change in Contract and Map