Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): W100-00-00-E003
Vendor/Entity Legal Name (if applicable): Buffalo Bayou Partnership
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with Buffalo Bayou Partnership, in the amount of $2,750,000, to improve the northern bank west of Jensen Drive to the Union Pacific Rail line upstream of Jensen Drive, by stabilizing the bank and restoring the trail link in the area. (Buffalo Bayou Watershed, Bond ID Z-02, Project ID W100-00-00-E003, Agreement No. 2020-100, Precinct 1).
end
Background and Discussion:
The northern bank of the Buffalo Bayou, from Jensen Drive to the Union Pacific Rail Line just upstream of Jensen Drive, was significantly compromised after Hurricane Harvey. With the eroding bank, a trail has also collapsed. This is for the request to amend the existing interlocal agreement (Agreement 2020-100) with Buffalo Bayou Partnership to include contribution of funds to stabilize this portion of Buffalo Bayou.
Expected Impact:
Reinforcing the bank will prevent future erosion of the bank, and allow BBP to restore the trail link in the area.
Alternative Options:
Without taking action, further erosion is likely, leading to additional problems, including conveyance issues.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
09/10/2019 |
2.b.3 |
ATN |
08/10/2021 |
144. |
Agreement |
Location: Buffalo Bayou at Jensen Drive
Address (if applicable):
Precinct(s): Precinct 1
Fiscal and Personnel Summary |
Service Name |
4.a.3 - Engineering Services |
|
SFY 22 |
FY 23 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$ |
$2,750,000 |
$ |
Total Incremental Expenditures |
$ |
$2,750,000 |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Bonds |
$ |
$2,750,000 |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$ |
$2,750,000 |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$ |
$2,750,000 |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: September 27, 2022
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Tina Petersen, Ph.D., P.E., Executive Director, Flood Control District
Attachments (if applicable): Agreement and Map