Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD., P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Termination
Project ID (if applicable): 171033020712
Vendor/Entity Legal Name (if applicable): Texas Department of Transportation
MWDBE Contracted Goal (if applicable):N/A
MWDBE Current Participation (if applicable):N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute a Mutual Termination Agreement with Texas Department of Transportation due to Local On-System Improvement Project - Mueschke 9 not being bid within a year of the agreement initiation. All other provisions of the original contract are unchanged and remain in full force and effect, Precinct 4.
end
Background and Discussion:
LOSA - Local On-System Agreement was executed on 7/1/2021 and had a term of one year if the project was not bid in that timeframe.
Expected Impact:
Harris County will need to obtain a new Local On-System Agreement to construct the project.
Alternative Options:
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
6/8/2021 |
|
Approved terms of Local On-System Agreement with TxDOT |
Location:
Address (if applicable): Mueschke 9
Precinct(s): Precinct 4
Fiscal and Personnel Summary |
Service Name |
|
|
SFY 22 |
FY 23 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$ |
$ |
$ |
Total Incremental Expenditures |
$ |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$ |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: 9/13/2022
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Kyle Hardy P.E., Assistant Project Manager , Engineering
Attachments (if applicable): Agreement