Harris County Logo
File #: 22-5558    Version: 1 Name:
Type: Utility Agreement Status: Passed
File created: 9/6/2022 In control: Commissioners Court
On agenda: 9/13/2022 Final action: 9/13/2022
Title: Request for approval to execute a Facilities Extension Agreement with CenterPoint Energy Houston Electric, LLC and to authorize the County Auditor to approve a Purchase Order for $8,531.00 for the cost associated with the installation of underground facilities in connection with Oak Glen Place East Subdivision Drainage Improvements at 14026 1/2 Sellers Road Houston, Tx 77060, UPIN 19101MF13601, Precinct 2.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E. PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Utility Agreement

 

Project ID (if applicable): 19101MF13601

Vendor/Entity Legal Name (if applicable): CenterPoint Energy Houston Electric, LLC

 

MWDBE Contracted Goal (if applicable): NA

MWDBE Current Participation (if applicable): NA

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval to execute a Facilities Extension Agreement with CenterPoint Energy Houston Electric, LLC and to authorize the County Auditor to approve a Purchase Order for $8,531.00 for the cost associated with the installation of underground facilities in connection with Oak Glen Place East Subdivision Drainage Improvements at 14026 ½ Sellers Road Houston, Tx 77060, UPIN 19101MF13601, Precinct 2.

end

 

Background and Discussion: CenterPoint requires signed Facilities Extension Agreement for easement request

for new service.

 

Expected Impact: If this is agreement is not moved forward the project it supports cannot begin.

 

Alternative Options: There are no alternate options as CenterPoint is the one and only entity we can deal with in these matters.

 

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Prior Court Action (if any): NA

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable):  14026 ½ Sellers Road Houston Tx 77060

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Facilities Extension

 

SFY 22

FY 23

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$8,531.00

$

$

Total Incremental Expenditures

$8,531.00

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

1080 - Infrastructure Fund

$8,531.00

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$8,531.00

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$8,531.00

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: September 13, 2022

Anticipated Implementation Date (if different from Court date): N/A

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Cameron J. McCraw, Project Manager, Engineering

Attachments (if applicable): Facility Extension Agreement