Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): UPIN 22101MF2GA01
Vendor/Entity Legal Name (if applicable): City of Houston
MWDBE Contracted Goal (if applicable):N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute an Interlocal Agreement with the City of Houston to construct improvements to improve Antoine Drive from West Mount Houston to US 290 and all related appurtenances, UPIN 22101MF2GA01, Precinct 1.
end
Background and Discussion:
Antoine Drive improvement from West Mount Houston Road to US 290 is a federal funded project. The City of Houston has the advancement funding agreement with TxDOT. The City manages the schematic design for the entire corridor and also will manage the construction. The interlocal agreement is to define the responsibilities for the segment under Harris County jurisdiction from north of West Gulf Bank Road to West Mount Houston Road. The proposed improvement will include the new four lane concrete road with 10 feet share-use-path on each side, storm sewer, bus stops, two signals, etc.
Expected Impact:
The proposed improvement will provide the safer condition for both traffic and pedestrian.
Alternative Options:
The alternative option for the agreement would be denial of the federal funding. This will increase the construction cost to Harris County.
Alignment with Goal(s):
X_ Justice and Safety
X_ Economic Opportunity
_ Housing
X_ Public Health
X Transportation
X_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
12/01/2015 |
2.a.d.5 |
Authorization to Negotiate |
04/26/2022 |
#20 |
Professional Service Agreement |
Location:
Address (if applicable): Antoine Dr from North of West Gulf Bank Road to West Mount Houston Road
Precinct(s): Precinct 1
Fiscal and Personnel Summary |
Service Name |
Interlocal Agreement |
|
SFY 22 |
FY 23 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$2,274,008.00 |
$ |
$ |
Total Incremental Expenditures |
$2,274,008.00 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
1070 - Mobility Fund |
$1,979,989.96 |
$ |
$ |
1070 - Mobility Fund |
$294,018.04 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$2,274,008.00 |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$2,274,008.00 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: September 13, 2022
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Mike Chang, Team Lead-CIP Road & Bridge Pct One, HCED
Attachments (if applicable): Contract