Department: Purchasing
Department Head/Elected Official: DeWight Dopslauf
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 210444
Vendor/Entity Legal Name (if applicable): Jerdon Enterprise, L.P.
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to Jerdon Enterprise, L.P. in the amount of $1,052,326 for construction of pedestrian trails along drainage ditch of Brays Bayou D100-00-00 under Addicks Clodine Road Bridge for Precinct 3, and for the County Clerk to execute any applicable bonds to be received (210444).
end
Background and Discussion:
Construction of Pedestrian Trails and undercrossing along Brays Bayou at Addicks Clodine Road bridge Precinct 4.
Expected Impact:
Schedule and Cost impact - TBC
Alternative Options:
n/a
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X_ Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
2/25/20 |
|
MUD120 ILA Reimbursement (design and Construction) |
1/4//22 |
|
MUD120 ILA (utility relocation) |
|
|
|
|
|
|
Location:
Address (if applicable):
Precinct(s): Precinct 3
Fiscal and Personnel Summary |
Service Name |
Addicks Clodine Undercrossing |
|
SFY 22 |
FY 23 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$ |
$ |
$ |
Total Incremental Expenditures |
$1,052,325.55 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Revenue - TRA |
$130,221.74 |
$ |
$ |
Grant |
$657,749.66 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$787,971.40 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: 08/23/22
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Jessica Cohen 281 948 4227, Joycie Adeyemi, Purchasing department
Attachments (if applicable): Letter and Bid Tab