Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E. PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Financial Authorization
Project ID (if applicable): UPIN 22102MF2EM01
Vendor/Entity Legal Name (if applicable): CenterPoint Energy
MWDBE Contracted Goal (if applicable): NA
MWDBE Current Participation (if applicable): NA
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of the Grant to Others Application fee with CenterPoint Energy for crossing of facilities within the transmission corridor, and for the County Auditor to approve a check for $1,600.00 for the cost associated with the Armand Bayou Project from Partnership Park to Armand Bayou Hike & Bike Trail - Fairmont Parkway Trail Head, UPIN 22102MF2EM01, Precinct 2.
end
Background and Discussion: CenterPoint requires an application fee for crossing of facilities within the transmission corridor.
Expected Impact: If this fee is not paid project cannot begin to move forward.
Alternative Options: There are no alternate options as CenterPoint is the one and only entity we can deal with in these matters.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
_ Flooding
_ Environment
X Governance and Customer Service
Prior Court Action (if any): NA
Date |
Agenda Item # |
Action Taken |
10/12/2021 |
94 |
ATN |
2/8/2022 |
106 |
Consultant Agreement for Professional Services |
Location:
Address (if applicable): Armand Bayou Project: From Partnership Park to Armand Bayou Hike & Bike Trail - Fairmont Parkway Trail Head
Precinct(s): Precinct 2
Fiscal and Personnel Summary |
Service Name |
Application fee |
|
SFY 22 |
FY 23 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$.00 |
$ |
$ |
Non-Labor Expenditures |
$1,600.00 |
$ |
$ |
Total Incremental Expenditures |
$1,600.00 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Other |
$1,600.00 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$1,600.00 |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$1,600.00 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: September 13, 2022
Anticipated Implementation Date (if different from Court date): NA
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Loretta Lau, Project Manager, Engineering
Attachments (if applicable): Application for CenterPoint Energy