Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Negotiation
Project ID (if applicable): 22/0292
Vendor/Entity Legal Name (if applicable): Professional Service Industries (PSI)
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable):N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to negotiate with Professional Service Industries (PSI) for Professional Engineering Services for Construction Materials Testing to construct Aldine Mail Route Road from Slater Lane to Aldine Westfield Road - UPIN 18102MF0SQ01 - Precinct 2.
end
Background and Discussion:
Reconstruction of paving subgrade, concrete pavement, asphaltic pavement and underground utilities on Aldine Mail Route Road from Slater Lane to Aldine Westfield Road.
Expected Impact:
Reconstructing these roadways and underground utilities will improve pavement conditions and drainage, thereby improving mobility and safety for all road users and flood resiliency for all adjacent properties. This agreement will allow the firm to conduct field and laboratory testing on soil, concrete, asphalt and various other construction materials. This testing will ensure the material’s compliance with Harris County Engineering and other governing bodies specifications as required by state law.
Alternative Options:
Construction materials testing is required by state law. Thus, alternatives include executing an agreement for similar services to a different vendor or cancelling this construction project.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any): N/A
Date |
Agenda Item # |
Action Taken |
|
|
|
Location:
Address (if applicable): Aldine Mail Route Road from Slater Lane.
Precinct(s): Precinct 2
Fiscal and Personnel Summary |
Service Name |
Professional Services - CMT |
|
SFY 22 |
FY 23 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$ |
$ |
$ |
Total Incremental Expenditures |
$ |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$ |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: September 13, 2022
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Corey D. Ritter, CMT Manager, CPD
Attachments (if applicable): N/A