Title: Request for approval of change in contract No. 2 with Solid Bridge Construction LLC, for a reinforced concrete spillway, resulting in no change to the contract amount. (Cypress Creek Watershed, Bond ID CI-012, Project ID K117-00-00-X003, Job No. 21/0156, Precinct 1, MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program).

Department: Flood Control District

Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): K117-00-00-X003                                          

Vendor/Entity Legal Name (if applicable): Solid Bridge Construction LLC

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Request Summary (Agenda Caption):

title

Request for approval of change in contract No. 2 with Solid Bridge Construction LLC, for a reinforced concrete spillway, resulting in no change to the contract amount. (Cypress Creek Watershed, Bond ID CI-012, Project ID K117-00-00-X003, Job No. 21/0156, Precinct 1, MWDBE Participation Goal: N/A - project was awarded prior to launch of County’s M/WBE Program).

end

 

Background and Discussion:

Unforeseen site conditions due to the difference in location of the existing sewer main and modifications to the design details of the rectangular concrete channel, manhole and concrete channel lining has resulted in plan changes. This requires an adjustment to plan quantities and addition of new pay items. The additional cost is being offset by underrunning pay items. No time extension is being requested.

 

Expected Impact:

This RCA is required to complete the District construction contract under original or needed revised scope.

 

Alternative Options:

This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

06/29/2021

385.

Award

05/10/2022

125.

Change in Contract No. 1

 

Location: Briarcreek Boulevard, east of Hardy Toll Road

Address (if applicable):

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

N/A

 

SFY 22

FY 23

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$

$

$

Total Incremental Expenditures

$

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Bonds

$

$

$

Other

$

$

$

Choose an item.

$

$

$

Total Current Budget

$

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: September 13, 2022

Anticipated Implementation Date (if different from Court date):

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Tina Petersen, Ph.D., P.E., Executive Director, Flood Control District