Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): UPIN 17102MF0N102
Vendor/Entity Legal Name (if applicable): Huitt-Zollars, Inc.
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Request Summary (Agenda Caption):
title
Request for approval to execute an amendment with Huitt-Zollars, Inc. in the amount of $110.00 for Professional Engineering Services to provide improvements to Atascocita Area Trails Phase 2, UPIN 17102MF0N102, Precinct 3, project was awarded prior to launch of County’s M/WBE Program.
end
Background and Discussion:
The County engaged Huitt-Zollars, Inc. in 2020, and now seeks Huitt-Zollars, Inc., to facilitate the re-design of a shared-use pedestiann/bike trail along Rogers Gully (G103-24-04). Huitt-Zollars, Inc. is qualified to perform these professional services. The firm is registered with the Harris County Engineering Department Professional Services Registry.
Expected Impact:
The project will provide safe mobility for pedestrians and bicyclists.
Alternative Options:
If no action is taken, the project may experience delays in improving mobility in the area.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
5/19/20 |
N/A |
Professional Engineering Services agreement approved on court agenda |
Location:
Address (if applicable): N/A
Precinct(s): Precinct 3
Fiscal and Personnel Summary |
Service Name |
Professional Engineering Services |
|
SFY 22 |
FY 23 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$110.00 |
$ |
$ |
Total Incremental Expenditures |
$110.00 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Other |
$110.00 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$110.00 |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$110.00 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: September 13, 2022
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Demetria Williams, Project Manager, HCED
Attachments (if applicable): Contract Documents