Department: Toll Road Authority
Department Head/Elected Official: Roberto Treviño, P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): N/A
Vendor/Entity Legal Name (if applicable): N/A
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute a utility services agreement with CenterPoint Energy Houston Electric, LLC in the amount of $61,337 for relocation of utility services for construction of the Lynchburg Ferry operations and maintenance building and warehouse (Precinct 2).
end
Background and Discussion:
The Lynchburg Ferry operations and maintenance building and warehouse project will replace the existing buildings. This project requires temporary relocation of the existing electrical services and new permanent electrical service to power the building and ferry vessels. When construction is complete there will be recurring usage costs associated with electrical usage.
Expected Impact:
This project aligns with Harris County’s goal of providing reliable, safe and sustainable transportation options to facilitate efficient movement of people and goods throughout the region.
Alternative Options:
No other identified solutions for this identified need.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
|
|
|
Location:
Address (if applicable): 1001 Independence Pkwy N, Baytown, TX 77520
Precinct(s): Precinct 2
Fiscal and Personnel Summary |
Service Name |
Lynchburg Ferry Operations and Maintenance |
|
SFY 22 |
FY 23 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$61,337 |
$ |
$ |
Total Incremental Expenditures |
$61,337 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
Revenue - TRA |
$61,337 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$61,337 |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$61,337 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: September 13, 2022
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Nicole Stuttz, Chief of Staff, Harris County Toll Road Authority
Attachments (if applicable): Agreement